RADIOCOMMUNICATIONS ACT 1992 No. 174, 1992 - SECT 41
Delays in preparing plans
41.(1) If the SMA thinks that preparation of a conversion plan or a
marketing plan may be unduly delayed because of difficulties in preparing the
plan so far as it relates to some of the frequencies within the part of the
spectrum in respect of which the plan is to be prepared, the SMA may:
(a) decide that, in order not to delay the preparation of a plan in
relation to frequencies for which the difficulties do not apply, the
task of preparing the plan should be divided into one of preparing
more than one plan; and
(b) prepare those plans at different times.
(2) Each of the plans so prepared is taken to have been prepared under section
38 or 39, as the case requires, and this Part applies to the preparation of
each plan accordingly.