Implementation of Federal Court order in respect of objection
decision - (1)
- When the order of the Federal Court in relation to the decision
becomes final, the Regulator must, within 60 days, take such action, including
amending any assessment or determination concerned, as is necessary to give
effect to the decision.
- (2)
- For the purposes of subsection (1):
- (a)
- if the order is made by the Federal Court constituted by a single Judge
and no appeal is lodged against the order within the period for lodging an
appealthe order becomes final at the end of the period; and
- (b)
- if the order is made by the Full Court of the Federal Court and no
application for special leave to appeal to the High Court against the order is
made within the period of 30 days after the order is madethe order
becomes final at the end of the period.