New South Wales Bills

[Index] [Search] [Download] [Related Items] [Help]


This is a Bill, not an Act. For current law, see the Acts databases.


BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT BILL 1999 (NO 2)





                                    New South Wales




Building and Construction Industry
Security of Payment Bill 1999


Contents
                                                                                 Page
          Part 1     Preliminary
                    1   Name of Act                                                2
                    2   Commencement                                               2
                    3   Object                                                     2
                    4   Definitions                                                3
                    5   Definition of "construction work"                          4
                    6   Definition of "related goods and services"                 6
                    7   Application of Act                                         6

          Part 2     Rights to progress payments
                    8 Rights to progress payments                                  8
                    9 Amount of progress payment                                   8
                   10 Valuation of construction work and related goods and
                      services                                                     9
                   11 Due date for payment                                        10
                   12 Effect of "pay when paid" provisions                        10



b99-071-p04.818
Building and Construction Industry Security of Payment Bill 1999

Contents

                                                                               Page

       Part 3     Procedure for recovering progress payments

              Division 1       Payment claims and payment schedules
                13 Payment claims                                               11
                14 Payment schedules                                            11
                15 Consequences of not paying claimant where no payment
                   schedule                                                     12
                16 Consequences of not paying claimant in accordance with
                   payment schedule                                             12

              Division 2       Adjudication of disputes
                17 Adjudication applications                                    13
                18 Eligibility criteria for adjudicators                        14
                19 Appointment of adjudicator                                   15
                20 Adjudication responses                                       15
                21 Adjudication procedures                                      15
                22 Adjudicator's determination                                  16
                23 Respondent's obligations following adjudicator's
                   determination                                                17
                24 Designated trust accounts                                    18
                25 Consequences of not complying with adjudicator's
                   determination                                                19
                26 Claimant may make new application if previous application
                   refused or not determined                                    20

              Division 3       Claimant's right to suspend construction
                               work
                27 Claimant may suspend work                                    20

              Division 4       General
                28 Nominating authorities                                       21
                29 Adjudicator's fees                                           21




Contents page 2
Building and Construction Industry Security of Payment Bill 1999

Contents

                                                                                  Page

                30 Exclusion of liability for adjudicator's acts and omissions      22
                31 Service of notices                                               22
                32 Effect of Part on civil proceedings                              23

       Part 4     Miscellaneous
                33   Act binds Crown                                                24
                34   No contracting out                                             24
                35   Regulations                                                    24
                36   Amendment of Commercial Arbitration Act 1984 No 160            24
                37   Savings and transitional provisions                            24
                38   Review of Act                                                  25


Schedules
                 1 Amendment of Commercial Arbitration Act 1984                     26
                 2 Savings and transitional provisions                              27




                                                                        Contents page 3
I certify that this PUBLIC BILL, which originated in the LEGISLATIVE ASSEMBLY, has
finally passed the LEGISLATIVE COUNCIL and the LEGISLATIVE ASSEMBLY of NEW
SOUTH WALES.

                                              Clerk of the Legislative Assembly.
                                              Legislative Assembly,
                                              Sydney,                       , 1999




                               New South Wales


Building and Construction Industry
Security of Payment Bill 1999
Act No            , 1999



An Act with respect to payments for construction work carried out, and related
goods and services supplied, under construction contracts; and for other purposes.




I have examined this Bill, and find it to correspond in all respects with the Bill as
finally passed by both Houses.


                            Chairman of Committees of the Legislative Assembly.


b99-071-p04.818
Clause 1          Building and Construction Industry Security of Payment Bill 1999

Part 1            Preliminary




The Legislature of New South Wales enacts:


Part 1 Preliminary
   1     Name of Act
              This Act is the Building and Construction Industry Security of
              Payment Act 1999.

   2     Commencement
              This Act commences on a day or days to be appointed by
              proclamation.

   3     Object
         (1) The object of this Act is to ensure that any person who carries out
             construction work (or who supplies related goods and services) under
             a construction contract is entitled to receive, and is able to recover,
             specified progress payments in relation to the carrying out of such
             work and the supplying of such goods and services.
         (2) The means by which this Act ensures that a person is entitled to
             receive a progress payment is by granting a statutory entitlement to
             such a payment in circumstances where the relevant construction
             contract fails to do so.
         (3) The means by which this Act ensures that a person is able to recover
             a progress payment is by establishing a procedure that involves:
             (a)    the making of a payment claim by the person claiming
                    payment, and
             (b)    the provision of a payment schedule by the person by whom the
                    payment is payable, and
             (c)    the referral of any disputed claim to an adjudicator for
                    determination, and
             (d)    the setting aside of money as security for payment of the
                    progress payment so determined.
         (4) It is intended:
             (a)      that this Act does not limit any other entitlement that a person
                      may have under a construction contract, or any other remedy
                      that a person may have for recovering any such other
                      entitlement, and
Page 2
Building and Construction Industry Security of Payment Bill 1999           Clause 3

Preliminary                                                                Part 1




              (b)     in particular, that the setting aside of money as security does not
                      prejudice any claim, counter-claim or defence that may be
                      raised in civil proceedings concerning the work to which a
                      payment claim relates, but merely ensures that money will be
                      available to satisfy those entitlements when they are finally
                      determined.

   4    Definitions
              In this Act:
              adjudicated amount means the amount of a progress payment that an
              adjudicator determines to be payable, as referred to in section 22.
              adjudication application means an application referred to in
              section 17.
              adjudication response means a response referred to in section 20.
              adjudicator, in relation to an adjudication application, means the
              person appointed in accordance with this Act to determine the
              application.
              authorised nominating authority means a person authorised by the
              Minister under section 28 to nominate persons to determine
              adjudication applications.
              business day means any day other than:
              (a)     a Saturday, Sunday or public holiday, or
              (b)     27, 28, 29, 30 or 31 December.
              claimant means a person by whom a payment claim is served under
              section 13.
              claimed amount means an amount of a progress payment claimed to
              be due for construction work carried out, or for related goods and
              services supplied, as referred to in section 13.
              construction contract means a contract or other arrangement under
              which one party undertakes to carry out construction work, or to
              supply related goods and services, for another party.
              construction work is defined in section 5.
              designated trust account means an account kept with a recognised
              financial institution (whether in the name of the respondent or
              otherwise) for the purpose of holding adjudicated amounts payable to
              claimants under this Act.


                                                                                    Page 3
Clause 4         Building and Construction Industry Security of Payment Bill 1999

Part 1           Preliminary




             due date, in relation to a progress payment, means the due date for the
             progress payment, as referred to in section 11.
             exercise a function includes perform a duty.
             function includes a power, authority or duty.
             payment claim means a claim referred to in section 13.
             payment schedule means a schedule referred to in section 14.
             progress payment means a payment to which a person is entitled
             under section 8.
             public authority means:
             (a)    a public or local authority constituted by or under an Act, or
             (b)    a Government Department, or
             (c)    a statutory body representing the Crown, or
             (d)    a statutory State owned corporation (and its subsidiaries) within
                    the meaning of the State Owned Corporations Act 1989,
             and includes any person exercising functions on behalf of any such
             authority, Department, body or corporation.
             recognised financial institution means a bank or any other person or
             body prescribed by the regulations for the purposes of this definition.
             related goods and services is defined in section 6.
             respondent means a person on whom a payment claim is served under
             section 13.
             scheduled amount means the amount of a progress payment that is
             proposed to be made under a payment schedule, as referred to in
             section 14.

   5     Definition of "construction work"
         (1) In this Act, construction work means any of the following work:
             (a)     the construction, alteration, repair, restoration, maintenance,
                     extension, demolition or dismantling of buildings or structures
                     forming, or to form, part of land (whether permanent or not),
             (b)     the construction, alteration, repair, restoration, maintenance,
                     extension, demolition or dismantling of any works forming, or




Page 4
Building and Construction Industry Security of Payment Bill 1999           Clause 5

Preliminary                                                                Part 1




                      to form, part of land, including walls, roadworks, power-lines,
                      telecommunication apparatus, aircraft runways, docks and
                      harbours, railways, inland waterways, pipelines, reservoirs,
                      water mains, wells, sewers, industrial plant and installations for
                      purposes of land drainage or coast protection,
              (c)     the installation in any building or structure of fittings forming,
                      or to form, part of land, including heating, lighting,
                      air-conditioning, ventilation, power supply, drainage, sanitation,
                      water supply, fire protection, security and communications
                      systems,
              (d)     the external or internal cleaning of buildings and structures, so
                      far as it is carried out in the course of their construction,
                      alteration, repair, restoration, maintenance or extension,
              (e)     any operation which forms an integral part of, or is preparatory
                      to or is for rendering complete, work of the kind referred to in
                      paragraph (a), (b) or (c), including:
                      (i)      site clearance, earth-moving, excavation, tunnelling and
                               boring, and
                      (ii)     the laying of foundations, and
                      (iii) the erection, maintenance or dismantling of scaffolding,
                               and
                      (iv) the prefabrication of components to form part of any
                               building or structure, whether carried out on-site or off-
                               site, and
                      (v)      site restoration, landscaping and the provision of
                               roadways and other access works,
              (f)     the painting or decorating of the internal or external surfaces of
                      any building or structure,
              (g)     any other work of a kind prescribed by the regulations for the
                      purposes of this subsection.
        (2) Despite subsection (1), construction work does not include any of the
            following work:
            (a)    the drilling for, or extraction of, oil or natural gas,
            (b)    the extraction (whether by underground or surface working) of
                   minerals, including tunnelling or boring, or constructing
                   underground works, for that purpose,
            (c)    any other work of a kind prescribed by the regulations for the
                   purposes of this subsection.


                                                                                    Page 5
Clause 6          Building and Construction Industry Security of Payment Bill 1999

Part 1            Preliminary




   6     Definition of "related goods and services"
         (1) In this Act, related goods and services, in relation to construction
             work, means any of the following goods and services:
             (a)    goods of the following kind:
                    (i)    materials and components to form part of any building,
                           structure or work arising from construction work,
                    (ii)   plant or materials (whether supplied by sale, hire or
                           otherwise) for use in connection with the carrying out of
                           construction work,
             (b)    services of the following kind:
                    (i)    the provision of labour to carry out construction work,
                    (ii)   architectural, design, surveying or quantity surveying
                           services in relation to construction work,
                    (iii) building, engineering, interior or exterior decoration or
                           landscape advisory services in relation to construction
                           work,
             (c)    goods and services of a kind prescribed by the regulations for
                    the purposes of this subsection.
         (2) Despite subsection (1), related goods and services does not include
             any goods or services of a kind prescribed by the regulations for the
             purposes of this subsection.

   7     Application of Act
         (1) Subject to this section, this Act applies to any construction contract,
             whether written or oral, or partly written and partly oral, and so applies
             even if the contract is expressed to be governed by the law of a
             jurisdiction other than New South Wales.
         (2) This Act does not apply to:
             (a)   a construction contract that forms part of a loan agreement, a
                   contract of guarantee or a contract of insurance under which a
                   recognised financial institution undertakes:
                   (i)    to lend money or to repay money lent, or
                   (ii)   to guarantee payment of money owing or repayment of
                          money lent, or
                   (iii) to provide an indemnity with respect to construction
                          work carried out, or related goods and services supplied,
                          under the construction contract, or



Page 6
Building and Construction Industry Security of Payment Bill 1999         Clause 7

Preliminary                                                              Part 1




              (b)     a construction contract for the carrying out of residential
                      building work (within the meaning of the Home Building Act
                      1989) on such part of any premises as the party for whom the
                      work is carried out resides in or proposes to reside in, or
              (c)     a construction contract under which it is agreed that the
                      consideration payable for construction work carried out under
                      the contract, or for related goods and services supplied under
                      the contract, is to be calculated otherwise than by reference to
                      the value of the work carried out or the value of the goods and
                      services supplied.
        (3) This Act does not apply to a construction contract to the extent to
            which it contains:
            (a)   provisions under which a party undertakes to carry out
                  construction work, or supply related goods and services, as an
                  employee (within the meaning of the Industrial Relations Act
                  1996) of the party for whom the work is to be carried out or the
                  related goods and services are to be supplied, or
            (b)   provisions under which a party undertakes to carry out
                  construction work, or to supply related goods and services, as
                  a condition of a loan agreement with a recognised financial
                  institution, or
            (c)   provisions under which a party undertakes:
                  (i)      to lend money or to repay money lent, or
                  (ii)     to guarantee payment of money owing or repayment of
                           money lent, or
                  (iii) to provide an indemnity with respect to construction
                           work carried out, or related goods and services supplied,
                           under the construction contract.
        (4) This Act does not apply to a construction contract to the extent to
            which it deals with:
            (a)   construction work carried out outside New South Wales, and
            (b)   related goods and services supplied in respect of construction
                  work carried out outside New South Wales.
        (5) This Act does not apply to any construction contract, or class of
            construction contracts, prescribed by the regulations for the purposes
            of this section.



                                                                                  Page 7
Clause 8            Building and Construction Industry Security of Payment Bill 1999

Part 2              Rights to progress payments




Part 2 Rights to progress payments

   8     Rights to progress payments
         (1) On and from each reference date under a construction contract, a
             person:
             (a)   who has undertaken to carry out construction work under the
                   contract, or
             (b)   who has undertaken to supply related goods and services under
                   the contract,
              is entitled to a progress payment under this Act, calculated by reference
              to that date.
         (2) In this section, reference date, in relation to a construction contract,
             means:
             (a)     a date determined by or in accordance with the terms of the
                     contract as:
                     (i)    a date on which a claim for a progress payment may be
                            made, or
                     (ii)   a date by reference to which the amount of a progress
                            payment is to be calculated,
                       in relation to work carried out or to be carried out (or related
                       goods and services supplied or to be supplied) under the
                       contract, or
              (b)      if the contract makes no express provision with respect to the
                       matter, the date occurring 4 weeks after the previous reference
                       date or (in the case of the first reference date) the date occurring
                       4 weeks after construction work was first carried out (or related
                       goods and services were first supplied) under the contract.

   9     Amount of progress payment
              The amount of a progress payment to which a person is entitled in
              respect of a construction contract is to be:
              (a)    the amount calculated in accordance with the terms of the
                     contract, or




Page 8
Building and Construction Industry Security of Payment Bill 1999          Clause 9

Rights to progress payments                                               Part 2




              (b)     if the contract makes no express provision with respect to the
                      matter, the amount calculated on the basis of the value of
                      construction work carried out by the person (or of related goods
                      and services supplied by the person) under the contract.

  10    Valuation of construction work and related goods and services
        (1) Construction work carried out under a construction contract is to be
            valued:
            (a)   in accordance with the terms of the contract, or
            (b)   if the contract makes no express provision with respect to the
                  matter, having regard to:
                  (i)     the contract price for the work, and
                  (ii)    any other rates or prices set out in the contract, and
                  (iii) any variation agreed to by the parties to the contract by
                          which the contract price, or any other rate or price set
                          out in the contract, is to be adjusted by a specific
                          amount, and
                  (iv) if any of the work is defective, the estimated cost of
                          rectifying the defect.
        (2) Related goods and services supplied under a construction contract are
            to be valued:
            (a)    in accordance with the terms of the contract, or
            (b)    if the contract makes no express provision with respect to the
                   matter, having regard to:
                   (i)     the contract price for the goods and services, and
                   (ii)    any other rates or prices set out in the contract, and
                   (iii) any variation agreed to by the parties to the contract by
                           which the contract price, or any other rate or price set
                           out in the contract, is to be adjusted by a specific
                           amount, and
                   (iv) if any of the goods are defective, the estimated cost of
                           rectifying the defect,
                      and, in the case of materials and components that are to form
                      part of any building, structure or work arising from construction
                      work, on the basis that the only materials and components to be
                      included in the valuation are those that have become (or, on
                      payment, will become) the property of the party for whom
                      construction work is being carried out.


                                                                                   Page 9
Clause 11          Building and Construction Industry Security of Payment Bill 1999

Part 2             Rights to progress payments




  11     Due date for payment
               A progress payment under a construction contract becomes due and
               payable:
               (a)   on the date on which the payment becomes due and payable in
                     accordance with the terms of the contract, or
               (b)   if the contract makes no express provision with respect to the
                     matter, on the date occurring 2 weeks after a payment claim is
                     made under Part 3 in relation to the payment.

  12     Effect of "pay when paid" provisions
          (1) A pay when paid provision of a construction contract has no effect in
              relation to any payment for construction work carried out (or for
              related goods and services supplied) under the contract.
          (2) In this section:
              money owing, in relation to a construction contract, means money
              owing for construction work carried out (or for related goods and
              services supplied) under the contract.
              pay when paid provision of a construction contract means a provision
              of the contract:
              (a)     that makes the liability of one party (the first party) to pay
                      money owing to another party (the second party) contingent on
                      payment to the first party by a further party (the third party) of
                      the whole or any part of that money, or
              (b)     that makes the due date for payment of money owing by the
                      first party to the second party dependent on the date on which
                      payment of the whole or any part of that money is made to the
                      first party by the third party.




Page 10
Building and Construction Industry Security of Payment Bill 1999      Clause 13

Procedure for recovering progress payments                            Part 3
Payment claims and payment schedules                                  Division 1



Part 3 Procedure for recovering progress payments

Division 1            Payment claims and payment schedules


  13    Payment claims
        (1) A person who is entitled to a progress payment under a construction
            contract (the claimant) may serve a payment claim on the person who
            under the contract is liable to make the payment.
        (2) A payment claim:
            (a)  must identify the construction work (or related goods and
                 services) to which the progress payment relates, and
            (b)  must indicate the amount of the progress payment that the
                 claimant claims to be due for the construction work done (or
                 related goods and services supplied) to which the payment
                 relates (the claimed amount), and
            (c)  must state that it is made under this Act.

  14    Payment schedules
        (1) A person on whom a payment claim is served (the respondent) may
            reply to the claim by providing a payment schedule to the claimant.
        (2) A payment schedule:
            (a)   must identify the payment claim to which it relates, and
            (b)  must indicate the amount of the payment (if any) that the
                 respondent proposes to make (the scheduled amount).
        (3) If the scheduled amount is less than the claimed amount, the schedule
            must indicate why the scheduled amount is less and (if it is less
            because the respondent is withholding payment for any reason) the
            respondent's reasons for withholding payment.
        (4) If:
            (a)       a claimant serves a payment claim on a respondent, and
            (b)       the respondent does not provide a payment schedule to the
                      claimant:
                      (i)    within the time required by the relevant construction
                             contract, or

                                                                           Page 11
Clause 14         Building and Construction Industry Security of Payment Bill 1999

Part 3            Procedure for recovering progress payments
Division 1        Payment claims and payment schedules


                      (ii)    within 10 business days after the payment claim is
                              served,
                      whichever time expires earlier,
               the respondent becomes liable to pay the claimed amount to the
               claimant on the due date for the progress payment to which the
               payment claim relates.

  15    Consequences of not paying claimant where no payment schedule
          (1) This section applies if the respondent:
              (a)    becomes liable to pay the claimed amount to the claimant under
                     section 14 (4) as a consequence of having failed to provide a
                     payment schedule to the claimant within the time allowed by
                     that section, and
              (b)    fails to pay the whole or any part of the claimed amount on or
                     before the due date for the progress payment to which the
                     payment claim relates.
          (2) In those circumstances, the claimant:
              (a)    may recover the unpaid portion of the claimed amount from the
                     respondent, as a debt due to the claimant, in any court of
                     competent jurisdiction, and
              (b)    may serve notice on the respondent of the claimant's intention
                     to suspend carrying out construction work (or to suspend
                     supplying related goods and services) under the construction
                     contract.
          (3) A notice referred to in subsection (2) (b) must state that it is made
              under this Act.
          (4) Judgment in favour of the claimant is not to be entered unless the court
              is satisfied of the existence of the circumstances referred to in
              subsection (1).

  16    Consequences of not paying claimant in accordance with payment
        schedule
          (1) This section applies if:
              (a)    a claimant serves a payment claim on a respondent, and
              (b)    the respondent provides a payment schedule to the claimant:
                     (i)     within the time required by the relevant construction
                             contract, or

Page 12
Building and Construction Industry Security of Payment Bill 1999       Clause 16

Procedure for recovering progress payments                             Part 3
Payment claims and payment schedules                                   Division 1


                      (ii)    within 10 business days after the payment claim is
                              served,
                      whichever time expires earlier, and
              (c)     the payment schedule indicates a scheduled amount that the
                      respondent proposes to pay to the claimant, and
              (d)     the respondent fails to pay the whole or any part of the
                      scheduled amount to the claimant on or before the due date for
                      the progress payment to which the payment claim relates.
        (2) In those circumstances, the claimant:
            (a)    may recover the unpaid portion of the scheduled amount from
                   the respondent, as a debt due to the claimant, in any court of
                   competent jurisdiction, and
            (b)    may serve notice on the respondent of the claimant's intention
                   to suspend carrying out construction work (or to suspend
                   supplying related goods and services) under the construction
                   contract.
        (3) A notice referred to in subsection (2) (b) must state that it is made
            under this Act.
        (4) Judgment in favour of the claimant is not to be entered unless the court
            is satisfied of the existence of the circumstances referred to in
            subsection (1).

Division 2            Adjudication of disputes


  17    Adjudication applications
        (1) If the scheduled amount indicated by a payment schedule is less than
            the claimed amount indicated in the payment claim, the claimant may
            apply for adjudication of the progress payment to be made (an
            adjudication application).
        (2) An adjudication application:
            (a)   must be in writing, and
            (b)   must identify the payment claim and the payment schedule to
                  which it relates, and
            (c)   may contain such submissions relevant to the application as the
                  claimant chooses to include.

                                                                            Page 13
Clause 17          Building and Construction Industry Security of Payment Bill 1999

Part 3             Procedure for recovering progress payments
Division 2         Adjudication of disputes


          (3) An adjudication application:
              (a)   must be made:
                    (i)     to an adjudicator chosen by agreement between the
                            claimant and the respondent (being a person who is
                            eligible to be an adjudicator as referred to in section 18),
                            or
                    (ii)    if no adjudicator is agreed on, to an authorised
                            nominating authority chosen by agreement between the
                            claimant and the respondent, or
                    (iii) if no nominating authority is agreed on, to an authorised
                            nominating authority chosen by the claimant, and
              (b)   must be made within 5 business days after the claimant receives
                    the payment schedule.
          (4) No agreement between the claimant and the respondent that was made
              before the claimant received the payment schedule has any effect in
              relation to the choice of an adjudicator under subsection (3) (a) (i).
          (5) A copy of the adjudication application must be served on the
              respondent.
          (6) This section does not limit the operation of any provision of the
              construction contract in relation to the resolution of disputes between
              the claimant and the respondent.
          (7) It is the duty of an authorised nominating authority to which an
              adjudication application is made to refer the application to an
              adjudicator (being a person who is eligible to be an adjudicator as
              referred to in section 18) as soon as practicable.

  18    Eligibility criteria for adjudicators
          (1) A person is eligible to be an adjudicator in relation to a construction
              contract:
              (a)    if the person is a natural person, and
              (b)    if the person has such qualifications, expertise and experience
                     as may be prescribed by the regulations for the purposes of this
                     section.




Page 14
Building and Construction Industry Security of Payment Bill 1999        Clause 18

Procedure for recovering progress payments                              Part 3
Adjudication of disputes                                                Division 2


        (2) A person is not eligible to be an adjudicator in relation to a particular
            construction contract:
            (a)    if the person is a party to the contract, or
            (b)    in such circumstances as may be prescribed by the regulations
                   for the purposes of this section.

  19    Appointment of adjudicator
        (1) An adjudicator accepts an adjudication application by causing notice
            of acceptance to be served on the claimant and the respondent.
        (2) On accepting an adjudication application, the adjudicator is taken to
            have been appointed to determine the application.

  20    Adjudication responses
        (1) The respondent may lodge with the adjudicator a response to the
            claimant's adjudication application (the adjudication response) at any
            time within:
            (a)   5 business days after receiving a copy of the application, or
            (b)   2 business days after receiving notice of an adjudicator's
                  acceptance of the application,
              whichever time expires later.
        (2) The adjudication response:
            (a)   must be in writing, and
            (b)   must identify the adjudication application to which it relates,
                  and
            (c)   may contain such submissions relevant to the response as the
                  respondent chooses to include.
        (3) A copy of the adjudication response must be served on the claimant.

  21    Adjudication procedures
        (1) An adjudicator is not to determine an adjudication application until
            after the end of the period within which the respondent may lodge an
            adjudication response.
        (2) An adjudicator is not to consider an adjudication response unless it
            was made before the end of the period within which the respondent
            may lodge such a response.


                                                                             Page 15
Clause 21         Building and Construction Industry Security of Payment Bill 1999

Part 3            Procedure for recovering progress payments
Division 2        Adjudication of disputes


          (3) Subject to subsections (1) and (2), an adjudicator is to determine an
              adjudication application as expeditiously as possible and, in any case:
              (a)    within 10 business days after the date on which the adjudicator
                     notified the claimant and the respondent as to his or her
                     acceptance of the application, or
              (b)    within such further time as the claimant and the respondent
                     may agree.
          (4) For the purposes of any proceedings conducted to determine an
              adjudication application, an adjudicator:
              (a)    may request further written submissions from either party and
                     must give the other party an opportunity to comment on those
                     submissions, and
              (b)    may set deadlines for further submissions and comments by the
                     parties, and
              (c)    may call a conference of the parties, and
              (d)    may carry out an inspection of any matter to which the claim
                     relates.
          (5) The adjudicator's power to determine an adjudication application is not
              affected by the failure of either or both of the parties to make a
              submission or comment within time or to comply with the
              adjudicator's call for a conference of the parties.

  22    Adjudicator's determination
          (1) An adjudicator is to determine:
              (a)   the amount of the progress payment (if any) to be paid by the
                    respondent to the claimant (the adjudicated amount), and
              (b)   the date on which any such amount became or becomes
                    payable.
          (2) In determining an adjudication application, the adjudicator is to
              consider the following matters only:
              (a)   the provisions of this Act,
              (b)   the provisions of the construction contract from which the
                    application arose,
              (c)   the payment claim to which the application relates, together
                    with all submissions (including relevant documentation) that
                    have been duly made by the claimant in support of the claim,

Page 16
Building and Construction Industry Security of Payment Bill 1999         Clause 22

Procedure for recovering progress payments                               Part 3
Adjudication of disputes                                                 Division 2


              (d)     the payment schedule to which the application relates, together
                      with all submissions (including relevant documentation) that
                      have been duly made by the respondent in support of the
                      schedule,
              (e)     the results of any inspection carried out by the adjudicator of
                      any matter to which the claim relates.
        (3) The adjudicator's determination must be in writing and must include:
            (a)   the reasons for the determination, and
            (b)   the basis on which any amount or date has been decided,
              if, before the making of the determination, either the claimant or the
              respondent requests the adjudicator to include those matters in the
              determination.

  23    Respondent's obligations following adjudicator's determination
        (1) If an adjudicator determines an adjudication application by determining
            that the respondent must pay an adjudicated amount to the claimant,
            the respondent:
            (a)     must pay that amount to the claimant, or
            (b)     must give security for payment of that amount to the claimant
                    pending the final determination of the matters in dispute
                    between them.
        (2) The security given by a respondent may be in any of the following
            forms:
            (a)    an unconditional promise by a recognised financial institution
                   to pay to the claimant, on demand, the adjudicated amount, or
            (b)    payment of the adjudicated amount into a designated trust
                   account, or
            (c)    such other form as may be agreed between the claimant and the
                   respondent.
        (3) If the respondent is a public authority, the security may be in the form
            of a certificate by the authority to the effect that sufficient money will
            be legally available for payment of any amount up to the adjudicated
            amount if and when any such amount becomes payable.




                                                                              Page 17
Clause 23          Building and Construction Industry Security of Payment Bill 1999

Part 3             Procedure for recovering progress payments
Division 2         Adjudication of disputes


          (4) Except with the consent of the parties, it is unlawful for the claimant
              to enforce any security given under this section until at least 2 business
              days after any matters in dispute between them in connection with the
              progress payment to which the security relates have been finally
              determined.
          (5) For the purposes of subsection (4), a determination becomes final:
              (a)    in the case of a determination from which there is no right of
                     appeal or review, when the determination is made, or
              (b)    in the case of a determination from which there is a right of
                     appeal or review, when the right of appeal or review expires or
                     (if the determination becomes subject to appeal or review
                     proceedings) when those proceedings have been finally
                     disposed of.

  24    Designated trust accounts
          (1) On paying money into a designated trust account as referred to in
              section 23 (2) (b), the respondent is to cause notice of that fact,
              together with particulars identifying the account and the recognised
              financial institution with which the account is kept, to be given to the
              claimant.
          (2) Money held in a designated trust account (including any interest
              accruing to such money) is taken to be held on the following trusts:
              (a)    to the extent to which the money is required to satisfy the
                     claimant's entitlements, the money is to be applied in
                     satisfaction of those entitlements,
              (b)    the claimant's entitlements in respect of an earlier progress
                     claim are to be satisfied before the claimant's entitlements in
                     respect of a later progress claim,
              (c)    to the extent to which any of the money remains in the account
                     after the claimant's entitlements have been fully satisfied, the
                     money is to be paid to the respondent.
          (3) Subject to subsection (2), the regulations may make provision for or
              with respect to the establishment and operation of designated trust
              accounts.




Page 18
Building and Construction Industry Security of Payment Bill 1999          Clause 24

Procedure for recovering progress payments                               Part 3
Adjudication of disputes                                                 Division 2


        (4) In this section, claimant's entitlements, in relation to money held in
            a designated trust account, means the amount (if any) to which the
            claimant becomes entitled after any matters in dispute between them
            in connection with the progress payment to which the money relates
            have been finally determined.
        (5) For the purposes of subsection (4), a determination becomes final:
            (a)    in the case of a determination from which there is no right of
                   appeal or review, when the determination is made, or
            (b)    in the case of a determination from which there is a right of
                   appeal or review, when the right of appeal or review expires or
                   (if the determination becomes subject to appeal or review
                   proceedings) when those proceedings have been finally
                   disposed of.

  25    Consequences of not complying with adjudicator's determination
        (1) This section applies if, on or before the relevant date, a respondent fails
            to do one or other of the following:
            (a)    to pay the whole or any part of the adjudicated amount to a
                   claimant,
            (b)    to give security for payment of the whole or any part of the
                   adjudicated amount to a claimant.
        (2) In those circumstances, the claimant:
            (a)    may recover the unpaid, or unsecured, portion of the
                   adjudicated amount from the respondent, as a debt due to the
                   claimant, in any court of competent jurisdiction, and
            (b)    may serve notice on the respondent of the claimant's intention
                   to suspend carrying out construction work (or to suspend
                   supplying related goods and services) under the construction
                   contract.
        (3) A notice referred to in subsection (2) (b) must state that it is made
            under this Act.
        (4) Judgment in favour of the claimant is not to be entered unless the court
            is satisfied of the existence of the circumstances referred to in
            subsection (1).




                                                                               Page 19
Clause 25          Building and Construction Industry Security of Payment Bill 1999

Part 3             Procedure for recovering progress payments
Division 2         Adjudication of disputes


          (5) In this section, relevant date means:
              (a)     the date occurring 2 business days after the date on which the
                      relevant determination is made under section 22, or
              (b)     if the adjudicator determines a later date under section 22 (1)
                      (b), that later date.

  26    Claimant may make new application if previous application refused or
        not determined
          (1) This section applies if:
              (a)    a claimant fails to receive an adjudicator's notice of acceptance
                     of an adjudication application within 4 business days after the
                     application is made, or
              (b)    an adjudicator who accepts an adjudication application fails to
                     determine the application within the time allowed by section 21
                     (3).
          (2) In either of those circumstances, the claimant:
              (a)     may withdraw the application, by notice in writing served on
                      the adjudicator or authorised nominating authority to whom the
                      application was made, and
              (b)     may make a new adjudication application under section 17.
          (3) Despite section 17 (3) (b), a new adjudication application may be made
              at any time within 5 business days after the claimant becomes entitled
              to withdraw the previous adjudication application under subsection (2).
          (4) This Division applies to a new application referred to in this section in
              the same way as it applies to an application under section 17.

Division 3            Claimant's right to suspend construction work


  27    Claimant may suspend work
          (1) A claimant may suspend the carrying out of construction work (or the
              supply of related goods and services) under a construction contract if
              at least 2 business days have passed since the claimant has caused
              notice of intention to do so to be given to the respondent under section
              15, 16 or 25.




Page 20
Building and Construction Industry Security of Payment Bill 1999       Clause 27

Procedure for recovering progress payments                             Part 3
Claimant's right to suspend construction work                          Division 3


        (2) The right conferred by subsection (1) exists only for so long as the
            respondent fails to comply with the requirements referred to in section
            15 (1), 16 (1) or 25 (1), as the case may be.
        (3) A claimant who suspends construction work (or the supply of related
            goods and services) in accordance with the right conferred by
            subsection (1) is not liable for any loss or damage suffered by the
            respondent, or by any person claiming through the respondent, as a
            consequence of the claimant not carrying out that work (or not
            supplying those goods and services) during the period of suspension.

Division 4            General


  28    Nominating authorities
        (1) Subject to the regulations, the Minister:
            (a)   may, on application made by any person, authorise the
                  applicant to nominate adjudicators for the purposes of this Act,
                  and
            (b)   may withdraw any authority so given.
        (2) A person:
            (a)   whose application for authority to nominate adjudicators for the
                  purposes of this Act is refused, or
            (b)   whose authority to nominate adjudicators is withdrawn,
              may apply to the Administrative Decisions Tribunal for a review of the
              Minister's decision to take that action.

  29    Adjudicator's fees
        (1) An adjudicator is entitled to be paid for adjudicating an adjudication
            application:
            (a)    such amount, by way of fees and expenses, as is agreed
                   between the adjudicator and the parties to the adjudication, or
            (b)    if no such amount is agreed, such amount, by way of fees and
                   expenses, as is reasonable having regard to the work done and
                   expenses incurred by the adjudicator.
        (2) The claimant and respondent are jointly and severally liable to pay the
            adjudicator's fees and expenses.


                                                                            Page 21
Clause 29          Building and Construction Industry Security of Payment Bill 1999

Part 3             Procedure for recovering progress payments
Division 4         General


          (3) As between themselves, the claimant and respondent are each liable to
              contribute to the adjudicator's fees and expenses in equal proportions
              or, if the adjudicator determines that the adjudication application or the
              adjudication response was wholly unfounded, in such proportions as
              the adjudicator may determine.
          (4) An adjudicator is not entitled to be paid any fees or expenses in
              connection with the adjudication of an adjudication application if he
              or she fails to make a decision on the application (otherwise than
              because the application is withdrawn or the dispute between the
              claimant and respondent is resolved) within the time allowed by
              section 21 (3).
          (5) Subsection (4) does not apply:
              (a)   in circumstances in which an adjudicator refuses to
                    communicate his or her decision on an adjudication application
                    until his or her fees and expenses are paid, or
              (b)   in such other circumstances as may be prescribed by the
                    regulations for the purposes of this section.

  30    Exclusion of liability for adjudicator's acts and omissions
               No action lies against an adjudicator or any other person with respect
               to anything done or omitted to be done by the adjudicator in good faith
               in the exercise of the adjudicator's functions under this Act.

  31    Service of notices
          (1) Any notice that by or under this Act is authorised or required to be
              served on a person may be served on the person:
              (a)    by delivering it to the person personally, or
              (b)    by lodging it during normal office hours at the person's
                     ordinary place of business, or
              (c)    by sending it by post or facsimile addressed to the person's
                     ordinary place of business, or
              (d)    in such other manner as may be prescribed by the regulations
                     for the purposes of this section.
          (2) Service of a notice that is sent to a person's ordinary place of business,
              as referred to in subsection (1) (c), is taken to have been effected when
              the notice is received at that place.



Page 22
Building and Construction Industry Security of Payment Bill 1999         Clause 31

Procedure for recovering progress payments                               Part 3
General                                                                  Division 4


        (3) The provisions of this section are in addition to, and do not limit or
            exclude, the provisions of any other law with respect to the service of
            notices.

  32    Effect of Part on civil proceedings
        (1) Subject to section 34, nothing in this Part affects any right that a party
            to a construction contract:
            (a)    may have under the contract, or
            (b)    may have under Part 2 in respect of the contract, or
            (c)    may have apart from this Act in respect of anything done or
                   omitted to be done under the contract.
        (2) Nothing done under or for the purposes of this Part affects any civil
            proceedings arising under a construction contract, whether under this
            Part or otherwise, except as provided by subsection (3).
        (3) In any proceedings before a court or tribunal in relation to any matter
            arising under a construction contract, the court or tribunal:
            (a)    must allow for any amount paid to a party to the contract under
                   or for the purposes of this Part in any order or award it makes
                   in those proceedings, and
            (b)    may make such orders as it considers appropriate for the
                   restitution of any amount so paid, and such other orders as it
                   considers appropriate, having regard to its decision in those
                   proceedings.




                                                                              Page 23
Clause 33          Building and Construction Industry Security of Payment Bill 1999

Part 4             Miscellaneous




Part 4 Miscellaneous

  33     Act binds Crown
               This Act binds the Crown in right of New South Wales and, in so far
               as the legislative power of Parliament permits, the Crown in all its
               other capacities.

  34     No contracting out
               A provision of any agreement (whether in writing or not) under which
               the operation of this Act is excluded, modified or restricted, or which
               has the effect of excluding, modifying or restricting the operation of
               this Act, is void.

  35     Regulations
          (1) The Governor may make regulations, not inconsistent with this Act, for
              or with respect to any matter that by this Act is required or permitted
              to be prescribed or that is necessary or convenient to be prescribed for
              carrying out or giving effect to this Act.
          (2) The regulations may, either unconditionally or subject to conditions,
              exempt:
              (a)   any specified person or class of persons, or
              (b)   any specified matter or class of matters,
               from the operation of this Act or of any specified provision of this Act.
          (3) The commencement of a regulation referred to in section 5, 6 or 7 does
              not affect the operation of this Act with respect to construction work
              carried out, or related goods and services supplied, under a
              construction contract entered into before that commencement.

  36     Amendment of Commercial Arbitration Act 1984 No 160
               The Commercial Arbitration Act 1984 is amended as set out in
               Schedule 1.

  37     Savings and transitional provisions
               Schedule 2 has effect.




Page 24
Building and Construction Industry Security of Payment Bill 1999     Clause 38

Miscellaneous                                                        Part 4




  38    Review of Act
        (1) The Minister is to review this Act to determine whether the policy
            objectives of the Act remain valid and whether the terms of the Act
            remain appropriate for securing those objectives.
        (2) The review is to be undertaken as soon as possible after the period of
            3 years from the date of assent to this Act.
        (3) A report on the outcome of the review is to be tabled in each House of
            Parliament within 3 months after the end of the period of 3 years.




                                                                          Page 25
                Building and Construction Industry Security of Payment Bill 1999

Schedule 1      Amendment of Commercial Arbitration Act 1984




Schedule 1          Amendment of Commercial Arbitration Act
                    1984

                                                                               (Section 36)



       Section 3 Repeal, transitional and application provisions

       Insert after section 3 (7):
               (8) Nothing in this Act affects the operation of Part 3 of the
                   Building and Construction Industry Security of Payment Act
                   1999.




Page 26
Building and Construction Industry Security of Payment Bill 1999

Savings and transitional provisions                                     Schedule 2




Schedule 2            Savings and transitional provisions

                                                                          (Section 37)



Part 1 Preliminary
   1    Savings and transitional regulations
        (1) The regulations may contain provisions of a savings or transitional
            nature consequent on the enactment of the following Acts:
              Building and Construction Industry Security of Payment Act 1999
        (2) Such a provision may, if the regulations so provide, take effect from
            the date of assent to the Act concerned or a later day.
        (3) To the extent to which such a provision takes effect from a date that
            is earlier than the date of its publication in the Gazette, the provision
            does not operate so as:
            (a)     to affect, in a manner prejudicial to any person (other than the
                    State or an authority of the State), the rights of that person
                    existing before the date of that publication, or
            (b)     to impose liabilities on any person (other than the State or an
                    authority of the State) in respect of anything done or omitted to
                    be done before the date of that publication.


Part 2 Provisions consequent on enactment of Building
       and Construction Industry Security of Payment Act
       1999
   2    Certain construction contracts not affected
              A provision of this Act does not apply to a construction contract
              entered into before the commencement of that provision.




                                                                             Page 27


 


[Index] [Search] [Download] [Related Items] [Help]