ELECTRICITY AMENDMENT ACT 2004 No. 50 - SECT 18

18 Amendment of sch 1 (Appeals against administrative decisions)

(1) Schedule 1, part 2--

renumber as schedule 1, part 3.

(2) Schedule 1--

insert--

Section Description of decision Court

Refusal of accreditation application

Imposition of accreditation condition, other than a condition mentioned in section 135AQ(3)

Deciding of ancillary matter, other than an ancillary matter mentioned in section 135AQ(3)

Refusal to transfer accreditation

Refusal to accept surrender of accreditation

Refusal to amend accreditation

Decision to take proposed action in relation to accreditation

Refusal to approve a direct method to work out eligible gas-fired electricity

Decision to give directions about how to work out factor used to work out eligible gas-fired electricity

Refusal to approve method to work out eligible gas-fired electricity

Fixing of annual loss factor

Fixing of baseline loss factor

Fixing of baseline for baseline customer of accredited power station

Decision that GEC was not validly created

Decision to give GEC surrender direction

Refusal to accept surrender of GEC

Decision to immediately suspend GEC

Fixing of suspension period for GEC

Decision to take proposed action in relation to GEC

Decision to make default assessment

Decision to make reassessment

Decision to make amended assessment

Decision about who is the liable person for liable load

Decision to require party to dispute to give stated document or information

Refusal of application for State development exemption application

Decision about extent to which liable load exemption is granted, other than an extent to which the applicant has agreed

Refusal of application to amend schedule for State development exemption

Refusal of liable load exemption application under part 5, division 6, subdivision 3

Decision about extent to which liable load exemption is granted, other than an extent to which the applicant has agreed

Refusal of liable load exemption application under part 5, division 6, subdivision 4

Decision to grant liable load exemption application under part 5, division 6, subdivision 4 for a load less than the load sought in the application

Refusal to amend liable load exemption

Decision to take proposed action in relation to liable load exemption

Refusal of application for approval as an auditor

135IG(1)(a) and 135IH

Imposition of condition on instrument of appointment as an approved auditor, other than a condition mentioned in section 135IH(6)

Revocation of approved auditor's appointment

Decision to give audit notice

Decision to carry out audit

Decision about method for working out amount of electricity load or amount of electricity sent out from a power station or delivered to an end user