After section 27AD—
insert—
'(1) The proponent of a coordinated project must give the Coordinator-General written notice of the following—
(a) a change of proponent for the project;
(b) a change in the proponent's contact details;
(c) if the proponent is a corporation, a change in the proponent's registered office.
'(2) The notice must be given—
(a) within 21 days after the change; or
(b) by any later time allowed by the Coordinator-General in writing.
'(1) The Coordinator-General may cancel a declaration made under section 26(1) for a coordinated project before completing a Coordinator-General's report for the project if—
(a) the proponent of the project makes a written request to the Coordinator-General to cancel the declaration; or
(b) the Coordinator-General considers that the proponent no longer has the capability to undertake and complete the EIS for the project; or
(c) the Coordinator-General considers it is in the public interest to cancel the declaration; or
(d) the proponent for the project changes; or
(e) the proponent substantially changes the project from that described in the initial advice statement mentioned in section 27(1)(a); or
(f) the proponent fails to comply with section 27AE in relation to the project.
'(2) If the Coordinator-General decides to cancel a declaration under subsection (1), the Coordinator-General must, within 14 days after the decision, give the proponent written notice of the decision and the reasons for it.
'(3) A decision to cancel the declaration takes effect on the later of—
(a) the day the written notice is given to the proponent; or
(b) the day of effect stated in the written notice. '.