PLANNING ACT 2016 - SECT 296
Development approvals and compliance permits
296 Development approvals and compliance permits
(1) Section 85 of this Act does not apply to a development approval or
compliance permit given under the old Act.
(2) Instead— (a) the old Act,
section 341 applies to the development approval, and the relevant period
mentioned in the section is taken to be the currency period; and
(b) the old
Act, section 409(2) applies to the compliance permit, and the relevant period
mentioned in the section is taken to be the currency period.
(3) For a
development approval to which the old Act, section 944A, applied— (a) for a
change application or extension application—the chief executive becomes—
(i) if the relevant entity stated in that section was the assessment
manager—the assessment manager; or
(ii) if the relevant entity stated in
that section was a concurrence agency—a referral agency; and
(b) if the
relevant entity stated in that section, as a concurrence agency, imposed a
condition of the approval—the chief executive is taken to have imposed the
condition.
(4) For any other development approval, the person who was the
assessment manager or a referral agency for the development application for
the approval continues as the assessment manager or referral agency for this
Act.
(5) For subsection (4), a compliance assessor under the old Act is taken
to be an assessment manager in relation to a change application, extension