(1) The coordinating agency must advise the local government of the coordinating agency's decision within 5 business days after--
(a) the end of the coordinating agency assessment period if there is an agreed State government response to the master plan application; or
(b) receiving the Minister's decision.
(2) The coordinating agency's decision must tell the local government one or more of the following--
(a) that it has no conditions to include in an approval of the proposed master plan;
(b) conditions (coordinating agency conditions) that must be included in an approval of the proposed master plan;
(c) that any approval must be for part only of the proposed master plan;
(d) that the master plan application be refused.
(3) Subsection (2) is subject to section 183.
(4) To remove any doubt, it is declared that the coordinating agency may exercise any power of the participating agency that the participating agency would have exercised if it had been making the decision.