(1) If the authority considers the application does not comply with a procedural requirement, the authority must give the applicant a notice stating that the applicant must comply with the requirement within a specified period of at least 28 days.
(2) However, the authority and the applicant may, within the period stated in the notice, agree to extend the period to a day (the agreed compliance day) after the end of the period.
(3) If the applicant does not comply with the requirement within the period stated in the notice or by the agreed compliance day, the authority may reject the application.
(4) If the authority decides to reject the application, the authority must give the applicant an information notice about the decision.