Part 1—Application fees |
|
1 |
Application for a licence under the Act |
$3 634.00 |
2 |
Application for the renewal of a licence under the Act |
$1 816.00 |
3 |
Application to vary or revoke a discretionary condition of a licence |
$1 816.00 |
4 |
Application for the approval of the Minister to vary a work program |
$1 816.00 |
5 |
Application to convert a production licence into a retention licence |
$1 816.00 |
6 |
Application for the authorisation of the Minister to alter or modify a
pipeline |
$1 816.00 |
7 |
Application to the Minister to consolidate adjacent licence areas, or to
divide a licence area |
$1 816.00 |
8 |
Application to the Minister to suspend a licence for a specified period |
$1 816.00 |
9 |
Application to the Minister for the approval and registration of a registrable
dealing |
$1 816.00 |
10 |
Application to have access to material included in the commercial register |
$181.00 |
Part 2—Annual licence fees (section 78) |
|
11 |
Preliminary survey licence |
$3 074.00 or $1.10 per km² of the total licence area, whichever
is the greater |
12 |
Speculative survey licence |
$3 074.00 or $1.10 per km² of the total licence area, whichever
is the greater |
13 |
Exploration licence— |
|
|
(a) in
relation to the first term of the licence |
$3 074.00 or $1.10 per km² of the total licence area, whichever is
the greater |
|
(b) in
relation to a licence granted on terms under which the licence is renewable
for 1 further term—in relation to the second term |
$3 074.00 or $1.70 per km² of the licence area during the second
term, whichever is the greater |
|
(c) in
relation to a licence granted on terms under which the licence is renewable
for 2 further terms— |
|
|
(i)
in relation to the second term |
$3 074.00 or $1.35 per km² of the licence area during the second
term, whichever is the greater |
|
(ii)
in relation to the third term |
$3 074.00 or $2.75 per km² of the licence area during the third
term, whichever is the greater |
|
(d) in
relation to a licence granted on terms under which the licence is renewable
for 3 further terms— |
|
|
(i)
in relation to the second term |
$3 074.00 or $1.25 per km² of the licence area during the second
term, whichever is the greater |
|
(ii)
in relation to the third term |
$3 074.00 or $1.70 per km² of the licence area during the third
term, whichever is the greater |
|
(iii)
in relation to the fourth term |
$3 074.00 or $3.45 per km² of the licence area during the fourth
term, whichever is the greater |
14 |
Retention licence— |
|
|
(a) in
relation to a petroleum retention licence |
$3 074.00 or $529.00 per km² of the total licence area,
whichever is the greater |
|
(b) in
relation to a geothermal retention licence or a gas storage retention licence
|
$3 074.00 or $132.00 per km² of the total licence area,
whichever is the greater |
15 |
Production licence— |
|
|
(a) in
relation to a petroleum production licence |
$3 074.00 or $529.00 per km² of the total licence area,
whichever is the greater |
|
(b) in
relation to a geothermal production licence or a gas storage licence |
$3 074.00 or $132.00 per km² of the total licence area,
whichever is the greater |
16 |
Pipeline licence |
$3 074.00 or $290.00 per km, whichever is the greater |
17 |
Associated activities licence— |
|
|
(a) in
relation to a licence to which section 57(1)(a) of the Act applies |
$3 074.00 or $1 538.00 per km 2 of the total licence
area, whichever is the greater |
|
(b) in
relation to a licence to which section 57(1)(b) of the Act applies |
$3 074.00 |
18 |
Special facilities licence |
$3 074.00 or $1 538.00 per km 2 of the total licence
area, whichever is the greater |