(1) In this regulation start-up notice , for a diving project, means a written notice, signed by or for the person giving it, dated and containing the following information:(a) the name, address and telephone number of the diving contractor for the project;(b) the name, address and telephone number of a person who can be contacted by the Safety Authority at any time during the project;(c) the date when diving is expected to begin;(d) the expected duration of the project;(e) the location of the project;(f) the depth to which divers will dive;(g) the purpose of the diving project;(h) the estimated number of people to be engaged in the project;(i) the breathing mixture to be used;(j) the title, document number and revision number of the diving project plan for the project.(2) The operator for a diving project must not allow diving on the project to begin if the operator has not given a start-up notice to the Safety Authority (a) at least 14 days before the day when diving is to begin; or(b) on another day as agreed between the Safety Authority and the operator.Penalty: In the case of (a) a body corporate, a fine not exceeding 100 penalty units; or(b) an individual, a fine not exceeding 50 penalty units.(3) If there is no operator for a diving project, the diving contractor must not allow diving on the project to begin if the diving contractor has not given a start-up notice to the Safety Authority (a) at least 14 days before the day when diving is to begin; or(b) on another day as agreed between the Safety Authority and the diving contractor.Penalty: In the case of (a) a body corporate, a fine not exceeding 100 penalty units; or(b) an individual, a fine not exceeding 50 penalty units.