(1) The compliance period for a fortification removal order begins on the day that the order takes effect and ends on the later of—
(a) the day that is 3 months after the day on which the order takes effect; or
(b) the day specified by—
(i) the Chief Commissioner under section 18; or
(ii) the Magistrates' Court by order under section 22.
(2) The compliance period for a fortification removal order does not include any period during which the operation of the order is stayed by a court.
(3) A period during which a fortification removal order does not have effect because it is stayed by a court does not count for the purposes of the period specified under subsection (1)(a).