MAJOR TRANSPORT PROJECTS FACILITATION ACT 2009 (NO. 56 OF 2009) - SECT 24

Determining 25 business day period for the preparation of scoping directions

The period of time specified in section 22(2) is not to be taken to include any business day falling within a period—

        (a)     commencing on the day a notice is given to a project proponent under section 23; and

        (b)     ending on the day the Planning Minister receives the information requested in the notice.