(1) This regulation applies in relation to the management plan that a responsible person is required, under regulation 9, to prepare for a financial year.
(2) If the responsible person is a major electricity company they must, before 31 March in the year that the financial year commences, submit the management plan to Energy Safe Victoria for approval.
Penalty: 20 penalty units.
(3) The responsible person must provide a copy of the management plan to Energy Safe Victoria on request within 14 days or such longer period as specified by Energy Safe Victoria.
Penalty: 20 penalty units.
(4) The responsible person must, if requested to do so by Energy Safe Victoria, provide further information or material in respect of the management plan within 14 days or such longer period as specified by Energy Safe Victoria.
Penalty: 20 penalty units.
(5) The responsible person must amend the management plan if instructed to do so by Energy Safe Victoria within 14 days or such longer period as specified by Energy Safe Victoria.
Penalty: 20 penalty units.
(6) The responsible person must not contravene a requirement of the management plan if the management plan is approved by Energy Safe Victoria.
Penalty: 20 penalty units.
(7) The responsible person must ensure that a copy of the management plan is—
(a) published on the responsible person's Internet site; and
(b) available for inspection at the responsible person's principal office in the State during normal business hours.
Penalty: 20 penalty units.