For the purposes of section 51 of the Act, a geothermal energy extraction development plan must contain—
(a) a description of the relevant existing geological and geothermal energy resource data that relate to the authority area, and of the interpretations of that data; and
(b) details of all proposed further data acquisition and studies to enhance geological and geothermal energy resource understanding in the authority area; and
(c) a geothermal energy resource management plan that—
(i) describes how the geothermal energy will be extracted; and
(ii) provides the reasons for adopting the proposed approach; and
(iii) estimates the future performance of the geothermal energy resource; and
(iv) specifies the proposed rate of recovery of geothermal energy.
__________________