55 .         Further information

        (1)         A permit authority to which an application is made may require the applicant to give the permit authority, within a specified time of not more than 21 days, any other document or information that it requires to determine the application and may require the applicant to verify the information by statutory declaration.

        (2)         The permit authority may refuse to consider an application if the applicant does not comply with a requirement under subsection (1) within the specified time.